Monitor Unix file systems restore operations

You can monitor the progress of different SnapCenter restore operations by using the Jobs page. You might want to check the progress of an operation to determine when it is complete or if there is an issue.

About this task

Post-restore states describe the conditions of the resource after a restore operation and any further restore actions that you can take.

The following icons appear on the Jobs page, and indicate the state of the operation:

  • In progress icon In progress

  • Completed icon Completed successfully

  • Failed icon Failed

  • Completed with warnings icon Completed with warnings or could not start due to warnings

  • Verification job is queued Queued

  • Cancel icon Canceled

Steps
  1. In the left navigation pane, click Monitor.

  2. In the Monitor page, click Jobs.

  3. In the Jobs page, perform the following steps:

    1. Click Filter icon to filter the list so that only restore operations are listed.

    2. Specify the start and end dates.

    3. From the Type drop-down list, select Restore.

    4. From the Status drop-down list, select the restore status.

    5. Click Apply to view the operations that have been completed successfully.

  4. Select the restore job, and then click Details to view the job details.

  5. In the Job Details page, click View logs.

    The View logs button displays the detailed logs for the selected operation.

Top of Page